The binding constraint on artificial intelligence is no longer chips, capital, or talent. It is electricity. US datacenters consumed roughly 176 terawatt-hours in 2023, about 4.4% of national electricity demand, and Lawrence Berkeley National Laboratory projects that figure reaching 325 to 580 TWh by 2028, as much as 12% of US consumption. The grid supplying that load is adding capacity at a fraction of the required pace: about 2,060 gigawatts of proposed generation and storage were still waiting in interconnection queues at the end of 2025, and PJM, the largest US grid, has cleared its capacity auction at the price cap three times running while falling short of its own reliability requirement. That mismatch, demand compounding at datacenter speed against supply moving at utility speed, is the most investable imbalance in the market today.
The demand shock, in terawatt-hours
The demand side of the ledger is compounding. The International Energy Agency estimates global datacenter consumption at roughly 415 TWh in 2024, about 1.5% of world electricity, and its base case has that doubling to around 945 TWh by 2030, with AI-accelerated servers accounting for the majority of the growth. The physics behind the curve is rack density: a legacy CPU rack draws 8 to 17 kilowatts, while a GB200-class GPU rack draws well over 100 kilowatts. The funding this build-out keep raising the bill: after first-quarter 2026 earnings, Microsoft, Alphabet, Amazon, and Meta guided to roughly $725 billion of combined 2026 capital expenditure, about 77% above the 2025 record of roughly $410 billion by the Financial Times tally, and Amazon and Alphabet raised again in July. Most of it is AI datacenters, and every dollar of it eventually needs a connection to a grid.
This piece is the physical-world sequel to a thesis Ezana Echo has already mapped: the consolidation analysis "They're Not Buying the Model" argued that 2026's $100-billion-plus tech M&A wave is a land-grab for proprietary data pipelines and workflow positions rather than for models. Every one of those pipelines terminates in a building that draws megawatts. The same logic that made data the scarce input upstream makes firm power the scarce input downstream, and the scarcity premium is migrating from software multiples to generation assets.
Against that demand curve, supply is arithmetic. US utility-scale capacity additions ran about 49 GW in 2024 with roughly 63 GW planned for 2025 in the EIA generator inventory, strong years by historical standards, yet most of it intermittent solar and storage rather than the around-the-clock firm power an requires. A gigawatt-class training campus needs its power at a 99.999% duty cycle; a solar farm delivers a 25% capacity factor. The gap between the bars and the line in the figure below is the whole story: demand measured in terawatt-hours consumed, supply measured in gigawatts that mostly cannot run at night.
FIG. 1 · DEMAND COMPOUNDS, SUPPLY CRAWLS
US DATACENTER POWER DEMAND (TWh, BARS, LEFT AXIS) VS. US UTILITY-SCALE CAPACITY ADDITIONS (GW, LINE, RIGHT AXIS) · 2024 ONWARD BLENDS ACTUALS, EIA PLANNED ADDITIONS, AND A MIDPOINT PATH OF THE LBNL 2028 SCENARIO RANGE.
Bar = datacenter demand (TWh, left axis); line = grid capacity additions (GW, right axis).
← swipe to explore →The interconnection queue is the real bottleneck
The US does not lack proposed generation; it lacks the ability to connect it. Lawrence Berkeley National Laboratory's "Queued Up" study counted a peak of nearly 2,600 GW of generation and storage in active interconnection queues at the end of 2023; by the end of 2025 the backlog had eased to about 2,060 GW, not because projects got built but because more than 750 GW withdrew in 2025 alone. The typical project built in 2024 took 55 months from interconnection request to commercial operation, and of all capacity that applied between 2000 and 2020 only 13% was operating by the end of 2025 while 75% had withdrawn. The one fuel growing in the queue is the one datacenters can use around the clock: active natural-gas requests rose 86% in 2025. Queue position, not on paper, is what determines when electrons actually flow, and the queue has become the single longest lead-time item in the entire AI supply chain.
The nuclear premium: PPAs, restarts, and co-location
Hyperscalers responded by going around the queue and straight to existing firm capacity, and nuclear is the asset they want. Microsoft signed a 20-year power purchase agreement with Constellation to restart the 835 MW Three Mile Island Unit 1 as the Crane Clean Energy Center, backed by a $1 billion Department of Energy loan; after a PJM study suggested grid connection could slip to 2031, FERC granted Constellation a waiver in June 2026 and the company now targets a restart in the second half of 2027. Amazon agreed to take power from Talen's Susquehanna plant, in a structure reworked after FERC rejected the original co-location amendment in November 2024. Meta signed a 20-year deal for the full 1,121 MW output of Constellation's Clinton plant from 2027, and in October 2026 Google and Constellation agreed an 11-unit uprate program. These contracts are running in reverse: instead of the utility locking in the customer, the customer is locking up the plant, for decades, at premium prices.
The market signal confirming the scarcity is the price of capacity itself. PJM, the grid operator spanning 13 states from Virginia's datacenter corridor to Chicago, saw its 2025/26 capacity auction clear at $269.92 per megawatt-day, up from $28.92 the year before, a roughly ninefold jump. Every auction since has cleared at the negotiated cap: $329.17 for 2026/27, $333.44 for 2027/28, and $325 for 2028/29 in July 2026. The cap is now doing the work the market cannot: PJM's own simulations put the uncapped 2027/28 price near $530, and the last two auctions were the first in PJM history in which the whole region fell short of its reliability requirement, by about 6,500 MW and then 6,831 MW. Nearly 5,100 MW of the 5,250 MW rise in the 2027/28 peak-load forecast was datacenters. Joe Dominguez has built Constellation's entire equity story on this repricing: the largest US nuclear fleet, running at a 93% capacity factor in the second quarter of 2026, suddenly holds the scarcest commodity in the AI economy, always-on carbon-free power that already exists.
FIG. 2 · CAPPED, NOT CLEARED
PJM BASE RESIDUAL AUCTION CLEARING PRICE, RTO, $/MW-DAY (UCAP), BY DELIVERY YEAR · DASHED = PJM SIMULATION WITHOUT THE PRICE CAP AND FLOOR · HOVER A YEAR FOR BOTH
Since 2026/27 the cap, not supply and demand, has set the price.
The energy industry cannot be the reason that America loses the AI race. Restarting a retired reactor for a single buyer would have been unthinkable five years ago; today it is the market clearing.
: Paraphrase of remarks by Joe Dominguez, Constellation CEO, at the Crane announcement, September 2024 (not a verbatim quote)
What cleared tells the same story from the supply side. Of the 138,318 MW PJM procured for 2028/29, 46% was natural gas, 20% nuclear and 18% coal; wind and solar together were 3%, because capacity accreditation pays for megawatts that show up on the coldest and hottest hours. Only 525 MW of new generation and uprates cleared in that auction, against a peak-load forecast that rose another 2,000 MW. The grid is being held up by the fleet it already has.
FIG. 3 · WHAT ACTUALLY CLEARED
PJM 2028/2029 BASE RESIDUAL AUCTION, CLEARED CAPACITY BY RESOURCE TYPE, % OF 138,318 MW UCAP · HOVER A SLICE FOR ITS SHARE
Firm, dispatchable fleets carried 84% of the capacity PJM could buy.
- Natural gas46%
- Nuclear20%
- Coal18%
- Demand response5%
- Hydro4%
- Wind, oil and solar5%
Three ways the build-out resolves
How the crunch resolves depends on two clocks: how fast reform accelerates the queue, and how fast hyperscalers route around it. FERC Order 2023 moved interconnection to first-ready-first-served cluster studies with real deposits, and the ADVANCE Act plus a string of pro-nuclear executive actions have compressed NRC licensing timelines, a genuine for both the queue and the reactor pipeline. The scenarios below trace the three paths the next four years can take, and what each one does to power prices and the trade.
FIG. 4 · THREE PATHS FOR THE POWER CRUNCH
BASE · ALT · BEAR: HOW GRID SUPPLY AND AI DEMAND RECONCILE THROUGH 2030, AND THE PRICE SIGNAL EACH PATH SENDS.
Three build-out scenarios; the kill switch is the indicator that flips the base case.
The uranium leg of the trade
If existing reactors are the scarce asset, their fuel is the scarce input behind it. Uranium spot prices rose from roughly $30 per pound in early 2021 to a peak near $106 in early 2024, dipped as low as about $64 in March 2025, and have climbed back to around $90-91 in November 2026, while the long-term contract price that utilities actually sign at reached $99 at the end of October 2026, the highest in TradeTech's series since 1996. It is a repricing with the classic anatomy of a : a decade of underinvestment after Fukushima, inventories drawn down, then a structural demand shock arriving faster than mines can respond. Cameco, which restarted McArthur River in 2022 after a four-year suspension, is the Western fuel cycle's anchor asset, and the US ban on Russian enriched uranium, signed in May 2024 with waivers running only through 2027, forces the re-shoring of a fuel chain in which Russia had supplied roughly a fifth to a quarter of US enrichment.
The small modular reactor names are the venture tranche of the same thesis. NuScale holds the first NRC-certified US SMR design, and Oklo, led by co-founder Jacob DeWitte, is pursuing a combined license for its Aurora fast reactor after an initial application was denied in 2022; Sam Altman chaired Oklo's board until stepping down in April 2025 as OpenAI began exploring energy deals directly. Centrus, the only US-licensed producer of the high-assay fuel most SMR designs need, delivered its first HALEU to the Department of Energy in late 2023. None of these companies has meaningful revenue from operating reactors yet; they trade on licensing milestones and letters of intent, which makes them optionality, not cash flow.
FIG. 5 · THE TERM PRICE LEADS
URANIUM U3O8, $/LB · SOLID = SPOT (CAMECO MONTH-END; NOV 2026 = MID-MONTH) · DASHED = LONG-TERM CONTRACT PRICE · MARCH 2025 TO NOVEMBER 2026 · HOVER A MONTH FOR BOTH
Utilities are paying more for decades of fuel than the spot market charges today.
The utility capex supercycle
For regulated utilities, the crunch is not a crisis but an order book. Investor-owned utility capital spending tracked by the Edison Electric Institute ran near $185-200 billion in 2025, with five-year plans totaling well over a trillion dollars, the largest peacetime infrastructure program in the sector's history. John Ketchum, NextEra's CEO, frames the demand backdrop as US power consumption growing roughly 55% over the next two decades, about six times the prior decade's pace. Every dollar of that spend earns a regulated return, which is why growth utilities now guide to 8-10% annual rate-base growth, bond-like businesses compounding at tech-adjacent rates because the runs through their balance sheets.
The physical constraints are where the cycle bites. GE Vernova ended the third quarter of 2026 with 122 GW of gas turbines in backlog or under slot-reservation agreements, expects at least 130 GW by year-end, and booked $29.3 billion of orders in the quarter, up 96% organically; its total backlog of $197 billion is on track to pass $200 billion. Large power transformer lead times, meanwhile, have stretched to two to three years, roughly double pre-2020 norms, by industry estimates. Scarcity along the equipment chain means the companies that already own capacity, or already hold delivery slots, capture the pricing; latecomers pay up or wait. That is the same dynamic playing out at every layer of this story, from queue positions to reactor fuel to transformer steel.
How to frame the trade
The investable map sorts into four baskets. Unregulated nuclear-heavy generators (CEG, VST, TLN) sell existing firm power into a market that suddenly wants decades of it. Regulated growth utilities (NEE, D) convert the same demand into rate-base compounding. The fuel cycle (CCJ, LEU, and the URA ETF as the basket expression) is a play on the enrichment the Russian import ban created. And the SMR tranche (SMR, OKLO, with GE Vernova's turbine franchise as the picks-and-shovels adjacency) is licensing-milestone optionality. The figure below plots the generator set on the axes that matter: how hard the fleet already runs, how big it is, and what the market pays for it.
FIG. 6 · WHO OWNS THE FIRM POWER
US POWER PRODUCERS · X = FLEET CAPACITY FACTOR (%) · Y = GENERATING CAPACITY (GW) · BUBBLE = MARKET CAP ($B) · SHADED ZONE = NUCLEAR-CLASS UTILIZATION AT SCALE, WHERE THE HYPERSCALER PPAS ARE BEING SIGNED. URANIUM AND SMR NAMES ARE EXCLUDED: CAPACITY-FACTOR AXES DO NOT APPLY TO MINERS OR PRE-REVENUE DEVELOPERS.
Up and to the right at size = always-on fleets the AI buyers want under contract.
← swipe to explore →The base case is that the crunch persists through the decade: LBNL's midpoint path implies US datacenter demand near 480 TWh by 2028, queue reform helps at the margin, and firm-power owners keep pricing power while the capex supercycle compounds through regulated rate bases. The power-constrained path is no longer hypothetical: the kill switch in FIG. 4 has already tripped in PJM. The bear case for the trade is a demand air-pocket: if AI training spend consolidates the way the M&A wave suggests capital already is, some announced gigawatts never get built, and the names priced for scarcity, particularly the pre-revenue SMR tranche, reprice hardest. The honest posture is to own the assets that exist (fleets, fuel, delivery slots) and treat the futures (SMRs, announced campuses) as options. The question that matters now is narrower than whether there is a shortage. It is who gets paid for it.
Who gets paid while the grid falls behind
A shortfall is a transfer. When a 1.2 GW campus cannot get a grid connection for five years, the value of speed moves to whoever can deliver megawatts sooner, and the bill lands on whoever cannot avoid paying for scarcity. The clearest winners are the owners of firm power that already exists. PJM's capacity price has risen more than elevenfold, from $28.92 to $333.44 per megawatt-day in three auctions, and the uncapped clears near $530 to $555 show how much headroom the cap is holding back. Constellation, Vistra and Talen sell into that market and into 20-year contracts with buyers who will pay a premium for certainty, so their earnings now track the length of the queue, not the price of gas.
The second winner is whoever sells the way around the queue. SemiAnalysis tracks about 75 GW of firm, binding behind-the-meter orders for AI datacenters, roughly 20 GW of them placed in the second quarter of 2026 alone, and Microsoft has signed more than 5 GW of on-site capacity this year, 2.7 GW with Chevron. That spending lands with turbine makers (GE Vernova, Siemens Energy, Mitsubishi Heavy), with fuel-cell suppliers that can switch a site on in months rather than years (Bloom Energy's Oracle agreement covers up to 2.8 GW, and NTT DATA committed to 900 MW in November 2026), and with gas producers and pipelines feeding Texas campuses where on-site generation is easiest to permit.
The third winner is the equipment chain inside and around the building, which gets paid whichever power source wins. Vertiv's organic orders more than doubled year over year in the third quarter of 2026, with sales up 61% to $4.31 billion, on demand for power distribution and liquid cooling at GB200-class densities. Quanta Services, the largest US transmission builder, and transformer and switchgear makers (Eaton, Hitachi Energy, and GE Vernova, which agreed a $9 billion purchase of Trench Group in October) sell into the same scarcity from the grid side. Regulated utilities such as NextEra convert the load into rate base. The fuel cycle (Cameco, Centrus) collects the slower, longer premium as term uranium contracts reprice.
FIG. 7 · WHO GETS PAID FOR THE SHORTFALL
SIX GROUPS THAT EARN FROM AI DEMAND OUTRUNNING GRID SUPPLY · ANCHOR = THE MOST RECENT REPORTED DATAPOINT FOR EACH · TAP A ROW FOR THE DOSSIER
Each row: how the group earns from the gap, its anchor datapoint, and what would end the trade.
The other side of the ledger is just as concrete. Households and industrial customers in PJM pay capacity charges set by those auctions, about $16.4 billion of cleared capacity in the 2028/29 auction alone, which is why governors forced the price cap and why rate cases are turning political. Developers who bought land and chips before securing power hold stranded optionality, and grid-dependent campuses in Northern Virginia wait behind faster markets such as Texas. The posture that follows is to own the assets that already exist or that sell the bypass (fleets, turbines, on-site power, cooling, fuel), treat the futures (SMRs, announced campuses) as options, and use the December 2026 PJM auction as the next mark of whether scarcity is still setting the price.